How to Compare Industrial Crane Quotations in 7 Steps
How to Compare Industrial Crane Quotations in 7 Steps
To compare industrial crane quotations, start by aligning the technical specifications and scope of supply. Each proposal should meet the same requirements for lifting capacity, span, lifting height, duty class and controls. Then check which quotation includes runway rails, power supply, transport, installation, commissioning and warranty. This gives you the information you need to compare the total cost of getting the crane operational at your facility.
Suppose a purchasing team receives two quotations for a 10-tonne overhead travelling crane. The first covers manufacture and transport. The second also includes runway rail installation, the power supply system and commissioning. Both cranes have the same rated capacity. With the first quotation, however, the buyer needs a separate budget and schedule for the remaining site work. A side-by-side comparison makes these responsibilities clear before the order is placed.
1. Compare capacity, dimensions and duty class
Begin with the rated lifting capacity, then compare the crane span, lifting height, hook approach and duty class. A bridge may travel the length of the production hall while its hook still falls short of a machine near the wall or an unloading point at the end of the runway. Mark each load pick-up and set-down point on the layout drawing and check it against the proposed crane’s hook coverage.
Give every supplier the same operating data. A crane used for occasional maintenance lifts has a different operating profile from one that feeds a production line throughout a shift. Share the typical and maximum load weights and the expected number of lifts per shift so each supplier can assess the same duty requirements.
2. Review the hoisting and travel units separately
The hoisting unit raises and lowers the load. The travel units move the crane bridge or trolley along its rails. Ask suppliers to specify the configuration, speed and control method for each motion. For options such as dual-speed operation, variable-frequency drives or PLC integration, confirm which motion each option applies to and whether it is included in the quoted price.
For example, a component may need to be lowered slowly onto an assembly fixture, while bridge travel is governed by the transfer distance across the hall. Describing these two movements separately makes it easier to compare the equipment in each proposal.
3. Assign responsibility for rails and site preparation
Identify who is responsible for the crane runway, rail supply and installation, surveys of existing infrastructure and site preparation. If you plan to reuse an existing runway, check whether the supplier’s quotation includes assessing it. For a new gantry crane, confirm the scope of the ground-level rails and associated civil works.
When the buyer is responsible for runway or ground preparation, put the site readiness date and the crane dispatch date in the same comparison sheet. This helps the installation team coordinate arrival with the completion of site work.
4. Clarify power supply, controls and specialised equipment
If a quotation says “electrical equipment included”, ask the supplier to specify the onboard electrical equipment, moving power supply system and work up to the plant’s electrical connection point. List pendant controls, radio remote controls and automation options separately so their costs and functions are clear.
This distinction also matters for process cranes. Scrap, billet and ladle handling each have specific requirements for how the load is picked up and released. If the application requires a lifting magnet, grab or lifting beam, ask whether the attachment and any required integration with the crane controls are included.
5. Check transport, installation and commissioning
One supplier may quote delivery from its factory, another may include transport to your facility, and a third may include installation and commissioning. For each proposal, check the delivery point, on-site unloading, supplementary lifting equipment, tests and handover documents.
Confirm what the quoted lead time refers to. Manufacturing completion, installation completion and the date the crane is ready for operation are separate milestones. Record the one your production schedule depends on.
6. Compare warranty, service and documentation
Record the warranty period, start date and coverage for each proposal. Ask who handles service requests, how spare parts are supplied and what operating and maintenance documents will be handed over. Eser Vinç Mühendislik includes installation and service among its stated capabilities.
If the crane is being installed on an operating production line, confirm when the documentation will be available and what support the supplier provides after commissioning. Your maintenance team can use those details to plan the handover.
7. Calculate the total installed cost
For each quotation, add any work excluded from the supplier’s price that will be required to bring the crane into operation. Use the same cost categories for every supplier. If the cost of an item is still unknown, mark it as pending confirmation and keep it visible in the comparison.
| Comparison item | What to look for in each quotation |
|---|---|
| Technical specification | Capacity, span, lifting height, duty class and hook coverage |
| Hoisting and travel units | Operating speeds, controls and included options |
| Runway and site work | Rail supply and installation, existing runway assessment and civil works |
| Power and controls | Electrical scope, control type, automation and below-the-hook attachments |
| Transport and installation | Delivery point, unloading and responsibility for installation equipment |
| Commissioning | Tests, handover documents and the date the system will be operational |
| Warranty and service | Warranty period, start date, coverage and after-sales support |
| Total installed cost | Quoted price plus required work the buyer will pay for separately |
Frequently asked questions about industrial crane quotations
Why can two 10-tonne crane quotations have different prices?
The span, lifting height, duty class, operating speeds and controls may differ even when both cranes have the same rated capacity. Pricing also depends on whether the supplier includes runway rails, power supply, installation and commissioning.
Are runway rails and installation included in an overhead crane quotation?
It depends on the supplier’s scope. Ask for rail supply, rail installation, crane installation and commissioning to be listed separately. If the project will use an existing runway, confirm who is responsible for assessing it.
What dimensions are needed for a jib crane quotation?
Provide the load weight, required jib reach, lifting height, slewing range and mounting location. A sketch showing where the load is picked up and set down helps the supplier evaluate column-mounted and wall-mounted options.
What should I send when requesting an industrial crane quotation?
Share your facility layout or site photos, load dimensions and weights, required lifting height, expected operating frequency and details of any existing runway. Include requirements for special controls, automation or below-the-hook equipment.
Based in Konya, Türkiye, Eser Vinç Mühendislik designs overhead travelling cranes, gantry cranes, jib cranes and process cranes around facility layouts and production requirements. Share your project dimensions and operating conditions to request a quotation with a defined technical scope.